At
12:00 on 12th September, the company's EPC project for the
Comprehensive Utilization of High-Carbon, Difficult-to-Burn Waste Dust
in Xinjiang reached a major milestone: the water pressure test for No. 2 Boiler passed successfully on the first attempt.
This signifies significant phased progress for the project, laying a
solid foundation for subsequent commissioning and overall operational
start-up.
To ensure the water pressure test's success, the company's project team actively coordinated with all participating construction units, overcoming construction challenges and advancing equipment installation to achieve the one-time pass for No. 2. Boiler The project is now accelerating comprehensively. Insulation and refractory work for Boiler No. 2 will be completed by mid-October , with integrated commissioning scheduled for late October. This will ensure production commencement by late November, creating value for the client and advancing the green energy industry.